The Building Cost Summary data dialog is accessed from the Tools menu.
Available in DesignBuilder v5.1 and later only
The dialog includes controls to allow you to select the cost calculation method. When either the NRM1 or UNIFORMAT II formats are selected, additional summary cost data for building can be entered to support the calculation.
Tip: The Cost data help topic provides an overview of the places in DesignBuilder where costs are entered.
Select the model to use from:
HVAC calculation method options are:
UNIFORMAT II is one of the most widely used element-based classification standard in North America. The standard is developed to reduce the effort in construction planning, scheduling and cost estimation in early design phases.
Elements are classified in three hierarchical levels of definition. Level 1 identifies seven Major Group Elements, such as the Substructure, Shell, and Interiors. Level 2 further subdivides Level 1 into Group Elements. The Shell, for example, includes the Superstructure, Exterior Closure, and Roofing. Level 3 breaks the Group Elements further into Individual Elements. Exterior enclosure, for example, includes Exterior Walls, Windows, and Exterior Doors.
Note: While DesignBuilder requires most of its data to be input using Level 2 elements, it reports costs using both Level 1 and 2 formats.
The latest version of the UNIFORMAT II standard can be purchased at: https://www.astm.org/Standards/E1557.htm
The data that is not already included in the model should be entered on the UNIFORMAT II tab of this dialog. Much of the data is structured as a cost per area or per each followed by the area or the number of items in that category.
The substructure costs are defined in the model through use of zone cost per floor area data (A10) and the constructions themselves within the below grade constructions (A20):
The cost of the superstructure is defined within the model through the area of the various exterior surfaces making up the superstructure and the cost per area of their constituent opaque and glazed constructions.
The cost of interior construction (C10) is defined within the model through the area of the various surfaces making up the interior construction and the cost per area of their constituent opaque and glazed constructions.
C10 Interior construction: includes partitions, interior doors and fittings
C20 Stairs: includes stair construction and stair finishes
C30 Interior finishes: includes wall finishes, floor finishes and ceiling finishes
Note that HVAC costs (D30) are included in the model.
D10 Conveying: includes elevators, lifts, escalators, moving walks and other conveying systems
D20 Plumbing: includes plumbing fixtures, domestic water distribution, sanitary waste, rain water drainage, and other plumbing systems
D30 HVAC: includes energy supply, heat generating systems, cooling generating systems, distribution systems, terminal & package units, controls and instrumentation, systems testing & balancing and other HVAC systems and equipment. This data is included zone by zone in the model on the HVAC tab and so does not need to be entered again here.
D40 Fire protection: includes sprinklers, standpipes, fire protection specialities and other fire protection systems.
D50 Electrical: includes electrical service & distribution, lighting & branch wiring, communication & security and other electrical systems.
E10 Equipment: includes commercial equipment, institutional equipment, vehicular equipment and other equipment
E20 Furnishing: includes fixed furnishings and movable furnishings
F10 Special construction: includes special structures, integrated construction, special construction systems, special facilities, special controls and instrumentation.
F20 Selective building construction: includes building elements demolitions and hazardous components abatement.
G10 Site preparation: includes site clearing, site demolition and relocations, site earthwork and hazardous waste removal/remediation.
G20 Site improvements: includes roadways, parkings lots, pedestrian paving, site development and landscaping.
G30 Site mechanical utilities: includes water supply, sanitary sewer, storm sewer, heating distribution, cooling distribution, fuel distribution and other site mechanical utilities.
G40 site electrical utilities: includes electrical distribution, site lighting, site communications & security and other site electrical utilities
G50 Other site construction: includes service and pedestrian tunnels and other site systems.
Z10 Design allowance: cost of design work.
Z20 Field Requirements, office overhead & profit: includes field requirements and office overhead & profits
Z30 Inflation allowance.
NRM1 – Order of Cost Estimating and Cost Planning for Capital Building Works (2012). NRM1 provides a standard format and sequence for priced works. It is published by the Royal Institute of Chartered Surveyors (RICS) for the purpose of providing best practice guidance on the preparation of order of cost estimates, elemental cost models, cost plans, cost analyses and benchmark analyses.
The latest version of this standard can be purchased at: http://www.rics.org/uk/shop/NRM-1-Order-of-Cost-Estimating-and-Cost-Planning-for-Capital-Building-19143.aspx
The data that is not already included in the model should be entered on the NRM1 tab of this dialog. Much of the data is structured as a cost per area or per each followed by the area or the number of items in that category.
The substructure costs are defined in the model through use of zone cost per floor area data and the constructions themselves within the below grade constructions.
The cost of the superstructure is defined within the model through the area of the various exterior surfaces making up the superstructure and the cost per area of their constituent opaque and glazed constructions. The exception is the stairs and ramps cost which is entered on this dialog.
Internal finishes data is entered for each surface using inheriting defaults on the Constructions tab.